From: 2024-03-02

To: 2024-03-05

Scrum Master: Hugo Correia

Product Owner: Duarte Cruz

Developers: Alexandre Cotorobai, Bernardo Figueiredo, Joaquim Rosa, André Oliveira

Sprint Goal

In order to complete the second milestone of our project, it is expectable to conclude the following sprints goals:

  • Functional requirements
  • Non-functional requirements
  • Actors and Use Cases
  • Data Domain Model
  • UI Mockups
  • Architecture and Design
  • Technology Stack
  • State of the Art
  • Update all the documentation
ExpectedQuantity
Tasks9
Epics1
Story Points45

Sprint Backlog

Task (Trail-*)DescriptionDeveloperStateStory Points
Trail-2State of the ArtJoaquim RosaDone5
Trail-3Functional RequirementsDuarte CruzDone5
Trail-4Actors and Use CasesBernardo FigueiredoDone5
Trail-5ArchitectureAndré OliveiraDone5
Trail-6Non-functional RequirementsDuarte CruzDone5
Trail-7Data Domain ModelAlexandre CotorobaiDone5
Trail-8UI MockupsBernardo Figueiredo, Hugo Correia, Duarte CruzDone5
Trail-9TechnologiesAllDone5
Trail-11Update DocumentationHugo CorreiaDone5

Task Status (Completed/Not Completed)

  • Trail-2: State of the Art
  • Trail-3: Functional Requirements
  • Trail-4: Actors and Use Cases
  • Trail-5: Architecture
  • Trail-6: Non-functional Requirements
  • Trail-7: Data Domain Model
  • Trail-9: Technologies
  • Trail-8: UI Mockups
  • Trail-11: Update Documentation

Sprint Review

ConcludedQuantity
Tasks7
Epics1
Story Points35

Sprint Retrospective

This sprint saw substantial completion of tasks, but UI Mockups and documentation updates were not finished due to time constraints as other tasks took longer than expected. The team will look at ways to better estimate the time required for complex tasks and adjust the sprint planning accordingly to ensure all tasks can be completed within the given timeframe. Going forward, this understanding will inform better allocation of efforts across tasks.

Sprint Burnup Chart

Burndown Chart

· 2 min read

During the development of our application we spread the work to be done by sprints. Each sprint had a duration of 1/2 weeks (except the first one) and at the end of each sprint we had a meeting to discuss the work done and the work to be done in the next sprint.

The distribution made is listed below:

SprintScrum MasterProduct OwnerDevelopers
1Hugo CorreiaDuarte CruzAlexandre Cotorobai, Bernardo Figueiredo, Joaquim Rosa, André Oliveira
2André OliveiraAlexandre CotorobaiJoaquim Rosa, Duarte Cruz, Hugo Correia, Bernardo Figueiredo
3Bernardo FigueiredoJoaquim RosaAlexandre Cotorobai, André Oliveira, Duarte Cruz, Hugo Correia
4Alexandre CotorobaiHugo CorreiaAndré Oliveira, Joaquim Rosa, Bernardo Figueiredo, Duarte Cruz
5Duarte CruzBernardo FigueiredoAlexandre Cotorobai, Hugo Correia, André Oliveira, Joaquim Rosa
6Joaquim RosaAndré OliveiraBernardo Figueiredo, Hugo Correia, Alexandre Cotorobai, Duarte Cruz
7André OliveiraBernardo FigueiredoJoaquim Rosa, Hugo Correia, Alexandre Cotorobai, Duarte Cruz
8Bernardo FigueiredoJoaquim RosaHugo Correia, Duarte Cruz, André Oliveira, Alexandre Cotorobai
9Alexandre CotorobaiJoaquim RosaAndré Oliveira, Hugo Correia, Bernardo Figueiredo, Duarte Cruz
10Hugo CorreiaDuarte CruzAlexandre Cotorobai, Bernardo Figueiredo, André Oliveira, Joaquim Rosa
11Duarte CruzAndré OliveiraHugo Correia, Alexandre Cotorobai, Bernardo Figueiredo, Joaquim Rosa